Categories
All Project Categories Dilapidation work Mezzanine Floors Office Refurbishments

Factory Refurbishment

Client: Image Factory
Value: £350k

Office and Factory Refurbishment project

This customer wanted a Factory Refurbishment having taken on the old Royal Mail building in Chippenham.

The first photograph below shows a £1m printing machine and Image Factory invested in two of them, along with taking over the old NHS distribution building on Bumpers Farm Industrial Estate. The complete building had to be refurbished, so the main factory along with the offices along the front of the building.

Factory Refurbishment

A large part of this project was electrical. The main factory had no power infra struture at all to power all of the print machines that the Image Factory owned as well as the new ones; so we had to install a heavy power buzz bar system into the factory and prepare the base and ground works for a new substation to be fitted.

In the main factory the floor had to be scrabbled to remove old oils in the concrete floor and then a high quality epoxy paint applied to the floor. All of the beams, walls and other surfaces also had to be painted.

Factory Refurbishment Photographs

Office Refurbishment

As well as the factory itself, the offices at the front of the building had to be completely stripped out and refurbished.

The mezzanine floor had to be turned around and a new jumbo stud fire wall constructed. Below the mezzanine floor we created a new reception area with fire rated ceiling, decorations and flooring. Upstairs included new ceilings, carpets, plastering and decorations as well as a new kitchen. Also fitted upstairs was a new office constructed from Komfort Kameo 75mm demountable partition.

If you need any advice or are thinking of an office refurbishment project please give us a call, we would love to talk to you, on 01380 738844